1. Read the conditions before comparing the number
A solar pile pull-out test value needs five conditions beside it: pile section, embedment depth, soil class, moisture or water table at the test, and test protocol with sample count. Without these, a buyer cannot establish a comparable basis or decide whether the result supports the proposed foundation.
The number is still a measurement. What is missing is its meaning for the purchasing decision. A higher reported load does not, on its own, identify a better pile or a suitable foundation for another site. Start by asking whether the reports describe the same question, then ask the project's foundation engineer whether the comparison is valid.
This article is a procurement checklist for ground mounted solar racking. It follows our frost-heave foundation calculation article, which addresses the separate question of winter ground movement. Here, the question comes earlier: what does the pull-out evidence actually represent?
A pull-out number travels with its conditions or it does not travel at all. Keep the supporting information in the comparison table, rather than separating the headline value from its report.

2. Record embedment depth separately from total pile length
Total pile length is a product dimension. Embedment depth describes how the installed pile relates to the ground. If different lengths remain above ground, equal total lengths do not establish equal embedment. Ask for the installation drawing, the surveyed ground reference and the installed pile-top elevation so the dimensions can be reconciled.
Identify the complete tested section too. A profile name alone may omit thickness, dimensions or an installation detail. For a ground screw, identify the shaft and helix arrangement shown in the test record. Keep the drawing revision beside the test identifier. A photograph can help locate the item, but should not replace the dimensioned record.
Do not turn a depth difference into a universal capacity multiplier. Increasing embedment may change which layers and foundation features participate, and the interpretation belongs to the project engineer. A result for one depth should not silently become a result for a revised length on the purchase order.
Use separate fields for specified and achieved embedment. If installation stopped early, ask for the recorded reason and the disposition approved for that location. The procurement task is to preserve that difference through delivery and installation records, not to decide that the unused length is unimportant.
3. Use soil class as context, not as a capacity table
The Unified Soil Classification System provides a common way to describe soil. ASTM D2487 covers classification using laboratory particle-size and plasticity information. Its public scope makes clear that classification is qualitative; design performance needs additional evidence. A USCS symbol is therefore useful context, but it is not a pile uplift capacity.
Request the soil investigation reference, sample or borehole identifier, and the layers relevant to the tested foundation. Broad descriptions such as clay, sand or mixed ground leave important questions unanswered. Ask where the classification came from and how the investigation relates to the actual test location. Do not assign a class from an installation photograph.
Also ask how density or consistency and changes between layers are represented in the geotechnical assessment. Two locations with the same headline soil name need not share the same conditions. A shallow description should not stand in for the complete embedded profile, and a nearby investigation should not be assumed to cover the whole array without an engineering basis.
For the supplier comparison, retain the original terminology and reference. If one report uses USCS and another uses a different classification system, ask the geotechnical engineer to explain the relationship. Do not create an equivalence by replacing both entries with a convenient word in the quotation spreadsheet.
4. Keep water conditions attached to the test date
Ask what was observed at the time of testing: the water-table observation, its location and timing, and any recorded moisture information. Where a measurement was not made, write that it was not recorded. A dry-looking surface does not document the conditions around the full embedded length.
Then ask a different question: which conditions did the foundation assessment consider for the completed project? An observation on one day and the condition selected for design serve different purposes. Keep both, including the source and the engineer responsible for interpreting the difference. Neither should quietly overwrite the other in a short supplier summary.
Rainfall, drainage work and construction changes are reasons to ask whether the original record still describes the proposed installation. This article does not prescribe a wet-season correction, or claim that every wetter test produces a particular change in capacity. Request a project-specific explanation instead of adding an assumed reduction to the reported load.
In cold regions, retain the distinction between a pull-out test in unfrozen ground and the winter assessment. The frost-heave article identifies the documents needed for that discussion. A warm-season result should not be labelled evidence of frozen-ground performance when that condition was not established in the test.
5. Read the protocol, individual results and installation record
ASTM D3689/D3689M-25, Standard Test Methods for Deep Foundation Elements Under Static Axial Tensile Load, covers measuring axial movement under static tensile loading. The public scope separates testing from the engineering use of results. Cite the edition and the actual procedure followed; a standard number alone does not describe a completed test.
For procurement review, ask for the complete load-and-movement record, the reported interpretation, any stated deviations and the basis for stopping the test. Keep the maximum applied load distinct from a reported failure load or an allowable design value. If the report uses one of those terms, preserve its definition and ask who accepted its use for the project.
A laboratory component test and a field foundation test also answer different questions. A pull test on a bracket does not establish the resistance of a pile in soil. Even within field tests, a single result and a mean from several locations are different summaries. Request individual results, locations and the stated sample count, including results that did not meet the project criteria.
Do not infer sample count from the number of rows on a summary page. Do not prescribe a universal minimum from this article either. The test program and its coverage are for the responsible engineer to specify. A buyer can still check that the delivered report matches the agreed program and identifies any missing locations.
Installation records should identify the method and equipment, achieved depth and any departures from the plan. For driven piles, request records of refusal and predrilling where relevant. For ground screws installed under a torque-based plan, request the recorded torque and the engineer's acceptance basis. No torque-to-capacity conversion is supplied here.

6. Separate structural reactions from foundation resistance
Solaracks uses SAP2000 for project-specific structural calculations within the agreed engineering scope. For ground systems, the handover should identify the pile-head reactions and the conditions behind them. Those reactions describe the actions the foundation must address; they should not be presented as measured soil resistance.
Ask for the sign convention, coordinate system, load combinations and the locations to which the reactions apply. Uplift, compression, horizontal action and moment should remain identifiable where relevant. A summary headed maximum load is not enough if it leaves the foundation engineer guessing which direction or combination it represents.
The project geotechnical engineer assesses the site evidence and field tests to select or confirm the foundation type and embedment. Coordinate that decision with the structural designer and the installation requirements. A change in racking geometry or foundation arrangement should trigger a review of the affected information, rather than an automatic reuse of the earlier schedule.
Solaracks does not publish a universal pile pull-out value in this article. The useful deliverable is a traceable project interface: structural demand, tested conditions and the foundation engineer's assessment. Our load calculation report guide provides related document-review questions. Software output alone does not replace the site investigation or establish ground screw uplift capacity.
7. Request an evidence pack before ranking supplier offers
Build the comparison around documents and unresolved questions. The following is an original buyer checklist, not a test procedure or an engineering acceptance rule. Ask each supplier to provide a page or drawing reference for every entry, and keep missing information visible.
- Tested item: pile section, dimensions, material identification, relevant features and drawing revision.
- Installed geometry: total length, achieved embedment, pile-top elevation and the ground reference used.
- Ground evidence: soil classification, investigation reference, relevant layers and the link to each test location.
- Water conditions: observed moisture or groundwater information, observation date and the separate design assessment.
- Test record: protocol, edition, procedure, dates, sample count, individual results and stated limitations.
- Original documents: the complete report, attachments, issuer identity and a contact route obtained independently from the issuer.
- Installation log: method, equipment, achieved depth, refusal, predrilling and other departures from the agreed plan.
- Engineering disposition: the assessment linking the evidence to the proposed foundation and the accepted changes, if any.
Our test-report verification guide explains the separate identity check. Confirming who issued a report does not establish that its result applies to your site. Keep authenticity, technical relevance and project acceptance as distinct entries in the purchase record.
Suppose two quotations provide different pull-out values but omit embedment and test location. Leave the ranking unresolved. Request the missing evidence and an engineering comparison before treating either result as a commercial advantage. This avoids awarding an offer on a difference that may come from different test conditions.
Send Solaracks the layout, site investigation, foundation test records and required structural design basis when requesting a ground-system quote. Identify provisional inputs so that the quotation and the engineering review use the same assumptions.

Sources checked 17 October 2026. Pile capacity is set by the project's geotechnical engineer from site evidence and tests, not by this article.