Canadian solar racking starts with the project permit basis

NBC 2025 was released on 22 December 2025. Publication does not make it the permit basis everywhere in Canada. The CBHCC adoption record currently lists Newfoundland and Labrador on the 2025 edition, most other jurisdictions on 2020 and Nunavut on 2015. Confirm the applicable local edition and transition rules before requesting a calculation package.

Start with the permit basis, before the hardware list

A Canadian solar quotation should identify the project address, authority having jurisdiction (AHJ), applicable building code and local amendments. The edition printed on a calculation cover must agree with that project basis. A newer national model code is useful reference material, but its publication alone does not establish the requirements for a particular permit.

The CBHCC publication announcement confirms the 2025 release and access to electronic copies. The separate adoption record shows why the procurement question is local. National model codes become the basis of provincial and territorial rules through adoption, sometimes with variations. A project may also involve a transition or an earlier submission. Ask the local reviewer which basis applies to this permit, rather than assuming the newest model edition governs.

For an EPC, the practical consequence is document control. State the agreed basis in the RFQ, design brief, calculation cover and drawing revision. If the basis changes, ask the engineer to identify which checks and components need revision before comparing the updated price with the earlier offer.

Canada's adoption record: a starting point for an RFQ

National model code to project permit basis decision chain

The table below transcribes the NBC edition, enforcement date and record date shown by CBHCC, checked on 13 October 2026. The final column matters: these are not thirteen separate confirmations of today's local permit requirements. All rows use the official CBHCC record; Newfoundland and Labrador also has the direct circular linked below.

Province or territoryNBC edition in recordEnforcement date shownRecord dated
Yukon2020, territorial variations1 Apr 2023Aug 2024
Northwest Territories2020, full adoption1 Oct 2024Aug 2024
Nunavut2015, full adoption8 Sep 2018Aug 2024
British Columbia2020, provincial variations8 Mar 2024Aug 2024
Alberta2020, provincial variations1 May 2024Aug 2024
Saskatchewan2020, provincial variations1 Jan 2024Aug 2024
Manitoba2020, provincial variations1 Jan 2024Aug 2024
Ontario2020, provincial variationsNot shownAug 2025
Quebec2020, provincial variations17 Apr 2025May 2025
New Brunswick2020, provincial variations1 May 2025May 2025
Prince Edward Island2020, full adoption31 Mar 2024Aug 2024
Nova Scotia2020, provincial variations1 Apr 2025Apr 2025
Newfoundland and Labrador2025, provincial variations12 Jul 2026Jul 2026

Some provisions have separate timing. CBHCC notes, for example, different commencement details for British Columbia's adaptable-dwelling and earthquake-design requirements. Ontario's row does not supply an enforcement date; this table deliberately leaves that field unresolved rather than inferring a date from the national edition number.

Newfoundland and Labrador's 21 January 2026 circular states 12 July 2026 as the coming-into-force date. It addresses plans submitted after that date and permits case-by-case consideration of designs already underway. Even this clear adoption date does not remove the need to ask about the individual project's submission and transition position.

Refresh the record when the quotation is issued, and again if the permit date changes. For another jurisdiction-by-jurisdiction example, see our ASCE 7-22 adoption resource. The Canadian project still needs its own local basis.

Change one: read the climatic values and load factors together

Site data, structural layout and design review are separate inputs

The 2025 text changes both the reference climatic inputs and the way principal snow and wind terms appear in strength combinations. In NBC 2025 Division B, Sentence 4.1.6.2.(1) defines the reference ground snow and associated rain values using an annual exceedance probability of 1 in 1,000. Sentence 4.1.7.3.(4) uses 1 in 500 for reference wind velocity pressure.

Table 4.1.3.2.-A uses 1.0S in the principal snow case and 1.0W in the principal wind case. The corresponding principal terms in NBC 2020 were 1.5S and 1.4W. These are selected terms, not complete design combinations: dead load, companion actions, importance factors and the other applicable cases still need attention. A procurement summary should never present two isolated coefficients as a complete design method.

The lower-looking multipliers do not demonstrate a lower design demand. The input probabilities changed too. Nor is it valid to take 2020 climatic values and simply substitute the 2025 multipliers. Require a consistent set of climatic inputs, coefficients and combinations for the selected edition. Ask for the underlying values and the resulting member and connection demands, rather than a claim that the new code automatically saves steel or aluminium.

The hardware question is specific: did the governing rail, post, connection or foundation check change? Ask the engineer for the old and new governing cases using the same documented geometry. A lighter member in one offer could reflect a different input, layout or assumption. It is not evidence of an edition benefit until those differences are reconciled.

Change two: snow exposure and thermal conditions need explicit inputs

NBC 2025 Article 4.1.6.2 includes a snow wind-exposure factor, Cw, derived from winter temperature and winter wind-speed inputs, subject to stated limits and exceptions. Sentence (4) requires Cw to be at least 1.0 in specified circumstances, including certain shelter, adjacent-surface drifting, and importance-category conditions. A general regional label such as “exposed roof” is not enough to justify a reduced value.

The basic roof snow factor, Cb, remains subject to roof geometry and specific provisions. The thermal factor, CT, is also part of the 2025 roof snow expression. Sentences (10) and (11) state its limits and require CT = 1.0 where the relevant indoor temperature or roof thermal transmittance is unknown. A buyer should be able to see which inputs were supplied and which conservative defaults were used.

For solar procurement, request a roof plan identifying geometry, adjacent levels, parapets, equipment and the array arrangement. Ask the project engineer how the relevant snow distributions and local effects were assessed for the mounting layout and supporting roof. Do not assume every support in a tilted array carries the same tributary demand, or that a reduced Cw value applies to every roof zone.

This can affect spacing and connection selection. A rail layout based only on convenient stock lengths is not a substitute for the design support layout. Have the calculation and drawing show where governing cases occur and which members or attachments they control. If insulation, heated occupancy or the roof build-up changes, return that change to the engineer rather than silently retaining the original thermal assumption.

The useful deliverable is a traceable input schedule and load layout, not an isolated coefficient copied into a sales table. It allows the roof engineer and mounting supplier to review the same physical arrangement before fabrication.

Change three: a CFD picture is not the specified wind-load method

NBC 2025 Division B, Sentence 4.1.7.1.(6) expressly excludes computational fluid dynamics from deriving specified wind loads on buildings and building components. A visually detailed CFD report should therefore not be accepted as that design-wind basis merely because it includes the proposed array.

Where the wind-tunnel procedure is used, Article 4.1.7.14 refers to ASCE/SEI 49, subject to its stated requirements. This is not a claim that every solar project requires a new wind-tunnel test. The responsible engineer must determine the applicable procedure and demonstrate that the data and assumptions cover the actual geometry and conditions being designed.

For a supplier's wind-tunnel evidence, request the report's identification, model arrangement, tested parameter ranges and the explanation of how its results apply to this project. Compare those ranges with module dimensions, tilt, row spacing, building height, roof location and surrounding conditions. A brand name on a report cover does not establish that an untested layout is covered.

Article 4.1.2.2 addresses loads and effects that are not listed. It does not provide an express permission to bypass the CFD restriction. If the designer proposes another standard or project-specific method for an unusual structure, have the engineer document the basis and resolve acceptance with the AHJ. Do not infer that a carport or ground array is exempt from design checks because it differs from a conventional roof installation.

Compare the project basis, rather than a saving percentage

A Toronto comparison needs checked climatic inputs, geometry, load assumptions and a consistent calculation method. A single illustrative example cannot establish the design for another roof or demonstrate a universal material-saving result. Ask for the complete comparison basis before accepting a percentage in a supplier presentation.

For a real Toronto RFQ, request two clearly labelled design summaries only if a comparison is needed: the accepted permit basis and the comparison basis. Keep the location, geometry, importance category and structural assumptions visible. Let the project engineer reconcile differences in the governing effects and resulting components. A comparison assembled from mixed editions cannot answer the purchasing question.

Five lines the calculation package should state

Five lines a Canadian calculation package should state

Before treating a quotation as technically comparable, ask for these five entries on its design-basis sheet:

  1. The applicable local code, national model edition, amendments and the project's transition position.
  2. The project location, climatic-data source, data edition or date, and who established the values.
  3. The structural arrangement, load distributions, importance category and assumptions supplied by others.
  4. The wind-design procedure and the scope of any supporting test evidence.
  5. The calculation issuer, issue date and revision linked to the matching drawings and BOM.

NBC 2025 Sentence 1.1.3.1.(1) starts with climatic values established by the AHJ; Sentence (2) provides the Appendix C fallback where they have not been established. Record which route was actually used. A city name and an unexplained snow value are not enough to reproduce the design basis.

Use the package to trace a result from input to governing check and then to the quoted component. Our guide to reading a mounting load calculation report provides a document-review starting point. For pile foundations, the frost-heave article identifies another set of site inputs that should accompany the structural basis.

The next step for an EPC is to send the project design brief with the RFQ: location, intended permit timing, roof or foundation information, module layout and the agreed code basis. Request a calculation package calculated to that basis, with revisions traceable to the quoted hardware.

For competing quotations, put the design basis beside the BOM before comparing totals. Flag any difference in module arrangement, support spacing, roof attachment, ballast or foundation assumptions. Ask who is responsible for each unresolved input and what information will close it. Keep a revision trail when the engineer changes an assumption, so the ordered components still match the reviewed layout.

Adoption records refreshed on 13 October 2026; cited NBC 2025 clauses checked on 10 October 2026. Recheck local adoption and project transition conditions before issuing a permit set. Clause references are to Division B of the NBC 2025 publication. This buyer guide is not a project design or engineering certification.

Frequently asked questions

Has NBC 2025 replaced NBC 2020 across Canada?

No. Adoption, local variations and transition conditions are jurisdiction-specific. Confirm the project permit basis with the AHJ.

Does a principal snow or wind factor of 1.0 mean a lighter structure?

No conclusion follows from the factor alone. Compare consistent climatic values, combinations and geometry, then review the governing checks with the engineer.

Can a supplier CFD report establish NBC 2025 design wind loads?

Sentence 4.1.7.1.(6) excludes CFD from deriving specified wind loads on buildings and building components. Request the applicable design procedure and project evidence.