Hook, separate LS connector and rail above timber and tiles.

Tile roof solar hook installation starts with the supporting timber, then the tile clearance and rail connection. This guide follows the hook, tile, rail and module sequence in the Solaracks manual filed as SR-H12. Check each connection while it remains visible, and use the project documents for the actual fixing specification.

Match the manual to the delivered kit

The source is C_Hook SR-H12 Manual, cover Version 1.0, dated 2024/09/03. Its installation section has eight numbered stages. The interior carries an older 2019 footer, so request the applicable issued manual and connection schedule for the delivered kit before construction. The sequence below explains those eight stages; it is not a replacement for the roof design or the electrical installation instructions.

The manual describes fixing to a wooden beam. For the rafter roof in this guide, establish which timber member is the designed support before setting out the hooks. A tile profile, a product-family name or a similar-looking hook does not establish that two fixing arrangements are interchangeable. The current SR-R8 tile-roof product family is a related selection reference, not evidence that every listed hook uses this assembly.

Before lifting parts onto the roof

Start with the approved array layout, roof assessment, fixing schedule, roof-covering detail and module instructions. Measure the actual support positions and compare them with the drawing. Hook spacing, rail overhang and edge-zone arrangements must come from the project calculation. The manual specifically directs installers to obtain the maximum rail support spacing from Solaracks or the dealer. Do not scale it from a picture.

Check the supporting timber before covering a connection. The manual rejects unsuitable supporting structures, including damaged or undersized members. If a surveyed fixing position does not reach the intended support, obtain a revised detail rather than moving the hook to whichever batten is easiest to reach. Follow local roof-work requirements and the site safety plan. A fixed hook is not a ladder rung.

Check delivered quantities and condition against the order. Identify the roof hook, its timber screws, LS connector, tilt-in module, rail, inter-module clamps and end clamps. The source labels its rails SR-R5 and SR-R1S, but labels the joiners "Splice for SR-R5" and "Splice for SR-R1". Resolve that naming difference against the issued bill of materials. Do not assume the SR-R1 label establishes compatibility with SR-R1S, or that the listed profiles are interchangeable.

Prepare the measuring tape, marking cord or pen, spirit level, drill and the correct driver for the supplied fasteners. The source lists a 6 mm Allen key or driver bit for its illustrated assembly. Use the tightening tool and setting specified for each joint. If the approved roof detail requires tile modification, arrange suitable tile-cutting equipment and the required dust, eye, hearing and hand protection before work begins.

1. Expose the support and fix the hook

Mark the fixing locations from the approved layout. At each mark, lift or remove the tile to expose the supporting timber. Present the hook in the orientation shown by the applicable connection detail, and check its relationship to the tile before fastening. Resolve a conflict between the timber position, tile profile and rail line while the connection remains accessible.

Fix the hook using the specified timber fasteners. The original instruction gives three self-tapping screws, a minimum of two, and a recommended tightening range. That wording does not select screw diameter, length, timber engagement or the required number for a new roof. Use the issued fixing schedule for those details, and do not transfer a tightening value from a different joint.

The source permits timber packing where necessary but does not provide a universal packing detail. Obtain the specified arrangement instead of choosing a thickness by eye. Do not bend the hook, drill extra holes or exchange components to make an unsuitable combination fit.

Check before covering: The hook reaches the designed support, the specified fasteners are present, and the timber and hook show no installation damage. Record a location-labelled photograph while the fixing is visible.

Original manual illustration of the hook-to-timber fixing and the checks needed before replacing the tile.
Original manual illustration of the hook-to-timber fixing and the checks needed before replacing the tile. Original manual artwork in an editorial checklist; not a construction drawing.

2. Replace the tile and check the hook exit

Return the removed tile over the hook, following the manual's second stage. Compare the hook exit with the approved covering detail and check that the tile is properly reinstated. The manual describes a local recess where necessary for the hook to pass through. It does not supply a universal clearance dimension, recess depth or weatherproofing method.

Whether a tile needs modification depends on the selected tile and hook detail. Follow the approved method for that roof covering; do not force a tile into place or turn an illustration into a cutting template. The source warns against using the fixed hook as a ladder because concentrated loading can damage the tile below.

Check before fitting the rail: The tile has been reinstated, the exit detail is accepted, and no damaged tile or unresolved covering issue is hidden. Photograph the finished exit as well as the concealed fixing recorded in step 1.

Original manual illustration of the reinstated tile, with a reminder to check the actual hook exit detail.
Original manual illustration of the reinstated tile, with a reminder to check the actual hook exit detail. Original manual artwork in an editorial checklist; not a construction drawing.

3. Connect and align the rail

Fix the LS connector to the hook. Insert the tilt-in module into the side channel of the specified rail, align the rail and fasten the bolt in the manual's order. Check that the channel component is seated as the assembly detail requires before final tightening. Check alignment across successive supports against the approved roof arrangement.

The hook-to-rail instruction does not state a connector torque. Do not apply the module-clamp value to this connection. Obtain the applicable value for the actual connector and fastener. Where a rail needs a splice, use the separate instructions for that rail and joiner; this installation paragraph does not establish a splice location or a thermal-expansion detail.

Check before modules: Correct rail profile, connector engagement, alignment and recorded tightening to the issued connection specification.

Original manual rail section showing the side channel, tilt-in module and LS connector interface.
Original manual rail section showing the side channel, tilt-in module and LS connector interface. Original manual artwork in an editorial checklist; not a construction drawing.

4. Position the inter-module clamp

The source's fourth stage begins with a pre-assembled inter-module clamp. Insert it from above, bring it against the module and leave it loosely engaged for the next module, as the applicable instructions require. This is an intermediate assembly stage, not the final clamped condition.

The source does not give a separate first-module end-restraint procedure. Obtain that procedure for the actual kit before beginning the module row. Check the module manufacturer's permitted clamp zones and frame compatibility together with the mounting instructions. A drawing of a clamp on a rail does not approve every position along a module frame.

Check: The specified first-module restraint is in place, the intended clamp is correctly engaged, and the crew can identify the permitted clamping positions.

5. Add the next module

Bring the next module into the documented inter-clamp arrangement and tighten that joint using its applicable specification. The manual also calls for anti-slip protection to sit in the rail channel of the lowest rail row. Identify that part and its correct seating in the issued assembly detail; do not substitute a visual guess when the supplied kit differs from the illustration.

Continue checking module alignment and the clamp-to-frame relationship as the row progresses. A connection partly hidden by the next module is harder to inspect later.

Check: Both module frames are in the specified clamping arrangement and the required anti-slip component is seated before advancing.

6. Finish the row

At the last module, complete the final inter-module clamp and end clamp as the sixth source stage describes. Use the tightening requirement assigned to that exact clamp and module combination. The historical manual's value is not a general setting for timber screws, rail connectors and all clamp families.

Check the completed row against the module layout. Record the connection checks before access becomes restricted by the next row. Where a clamp, fastener or frame differs from the documented combination, resolve the difference before continuing.

Check: End restraint, inter clamps, module alignment and the applicable tightening records are complete for the row.

7. Continue the remaining rows

The manual then directs the installer to continue the next row. Repeat the applicable module installation sequence with the issued first-module restraint procedure, checking each row against the layout. Keep row and fixing identifiers consistent between photographs, the drawing and the inspection record.

Do not treat progress across the roof as acceptance of an unresolved earlier connection. Keep incomplete locations recorded until the responsible installer has corrected and rechecked them.

Check: Installed module and support counts match the approved arrangement, and each row has a completed inspection record.

8. Complete the specified bonding work and handover

The final source stage names and illustrates the Solaracks rail grounding system. It does not provide a complete electrical method, conductor size, lug count or test limit. Qualified electrical personnel must use the project electrical design and applicable instructions for bonding, earthing and verification. An overview illustration cannot establish that electrical commissioning is complete.

For the structural handover, retain the concealed-fixing photographs, finished tile-exit photographs, rail checks, connection-specific tightening records and the marked-up layout. Record any correction by location and close it after inspection. These records are a suggested handover checklist, not extra installation dimensions from the manual.

For a different roof attachment, see the BL600 and RH4 installation guide. Its metal-roof clamp procedure does not replace this timber fixing detail. The BL600 and RH4 maintenance guide also illustrates how photographs and connection records support later inspection; its hardware-specific checks remain separate.

The sequence follows C_Hook SR-H12 Manual, cover Version 1.0, 2024/09/03; construction values follow the applicable issued documents. Hook spacing comes from the project calculation.

Frequently asked questions

Does every tile need cutting or grinding?

No. The source describes a recess only where necessary at the hook exit. Use the approved detail for the actual tile and hook. The manual does not give one clearance or cutting depth for every tile profile.

How far apart should the hooks be?

Use the project calculation and approved layout. The manual directs installers to obtain maximum rail support spacing from Solaracks or the dealer. A general example or a photograph cannot set the spacing for a different roof.

Can the hooks be fixed only to tile battens?

The documented fixing stage attaches the hook to a wooden beam. For a rafter-supported design, the fasteners must reach the designed rafter connection. The source does not authorize replacing that connection with batten-only fixing. Resolve the actual support detail before installation.

Get an engineered mounting quote for your project.

Share drawings, module layout, site location, wind load, snow load and corrosion environment. Solaracks will recommend the system, material, layout and packing approach.